Client:Tarong Energy
Fleurieu Peninsula
2003
Design and construct
$3.5m
Starfish Wind Farm required an upgrade to the Cape Jervis, Yankalilla and Willunga Substations to accept power generated by the wind farm.
We were required to design, supply, construct and commission upgrades to Cape Jervis, Yankalilla & Willunga substations, including earthworks, footings and ducts. Substation plant included:
We were also required to design, supply, construction and commission transformer, bus, line and islanding protection to Starfish Wind Farm, national grid metering, SCADA, communications and AC / DC auxiliaries.